Signing of the Contract
The repair and refit was being undertaken by FSUE Sevmash, the state owned shipyard at Severodvinsk, Russia. The R&R was scheduled to have been completed within 52 months. Though the refurbishment process was started in right earnest, soon it was realized that the work and equipment requiring replacement was significantly higher than originally estimated. Entire length of cable, large portions of steel hull, motors, turbines and boilers, etc. would have to be completely replaced with resulting in cost escalation and time slippage.
A protracted renegotiation for arriving at a mutually acceptable price for refurbishment was held in the ensuing months. Finally, in Dec 2009, the Indian and the Russian sides arrived at an agreement on the final price of delivery of this ship. More significantly, it was agreed that the delivery of the ship would take place only in the year 2012. Though the re-negotiated price was significantly higher than what was originally agreed upon, the fillip that the addition of Gorshkov would give to the Blue water requirements of Indian Navy compensated the greater price.
The Journey of Admiral Gorshkov (nee Baku)
The journey of ‘Vikramaditya’ began as the Kiev class aircraft carrying cruiser ‘Baku’. Developed from the Moskva class helicopter carrying guided missile cruisers the Kiev class was a pioneering Soviet era design, featuring a flight deck arrangement capable of operating fixed wing VTOL fighters for the first time in the Soviet Navy. Baku was constructed by Chernomorsky Ship Building Enterprise, Nikolayev (now in Ukraine). About 400 enterprises and nearly 1,500 – 2,000 workers from different republics of USSR took part in building of the ship. The ship was commissioned on 20 Dec 1987. Conceived as an armed cruiser, Baku was heavily armed with twelve Anti-Ship Missile launchers, ten gun mounts of differing calibre and rocket launchers and depth charges. The air element comprised Yak-38 aircraft.
‘Baku’ was envisioned to be a full-fledged aircraft carrier by Admiral SG Gorshkov, however, due to conflicting dynamics at that time, the ship turned out as the last ‘compromise’ ship of the Kiev series. After her development and construction, it became clear to the Soviet leadership that the vision of Admiral Gorshkov of a classical aircraft carrier with ship borne aircraft as the primary weapons was indeed the most logical way ahead to develop the surface forces. On 07 Nov 1990, the ship was named after Admiral Sergey Georgiyevich Gorshkov.
Baku/Admiral Gorshkov began its active operational service with the Northern Fleet and was deployed in the Mediterranean Sea and remained in active service till 1992 and thereafter continued in service albeit with limited operational deployments. The ship was finally decommissioned in 1996.
The Transformation
Admiral Gorshkov was put in hibernation after her last sailing in 1995. With most of her equipment lying un-utilised since then, the task of breathing life and converting her from a VTOL (Vertical Takeoff and Landing) missile cruiser carrier to a STOBAR aircraft carrier involved substantial degutting, equipment removal, refit and re-equipping. The major works envisaged were modification of flight deck to include ski-jump and arrester gear; modification of bulbous bow, aft aircraft lift & ammunition lifts; modification of 1750 out of 2500 compartments; installation of new main boilers; installation of new and additional Diesel Generators; replacement of existing distilling plants; fitment of Reverse Osmosis plants, new AC plants and Refrigeration plants and installation of new sensors and equipment. In 2007, as the refit and repair of the ship was in progress, the yard realized that the scope of work was much larger than initially estimated and so a revised timeline for completion of the task of modernization was agreed upon by both Russian and Indian sides. With a revised timeline the delivery of ship was expected by end 2012.
A Peek at the Scope of Work
Creation of Ski Jump
Creation of the flight deck with structural modification to convert the VTOL carrier to a STOBAR carrier was the most intricate and arduous. The task involved installation of Sponsons to increase the breadth at the Flight Deck and a fitment of a new 14 degree Ski jump, strengthening of arresting gear area, strengthening of run way area and elongation of the aft end to generate the required length of landing strip aft of the arresting gear. In all 234 new hull sections were installed to achieve the desired shape. Total steel work for carrying out structural modification on flight deck amounted to 2500T.
Modification of Super structure
The superstructure was modified to accommodate a host of sensors and equipment such as radars, Electronic Warfare suite and Action Information Organisation system and other systems to suit the requirements of ship borne fighters and rotors. A very unique structural modification that was carried out on board the ship was the installation of the aft mast for accommodating various communication antennae.
Machinery Modification
Vikramaditya in its older avatar was powered by boilers fuelled by heavy oil. The re-equipping included replacement of these old boilers with state of the art boilers utilizing LSHSD and providing a steam capacity of 100 Tonnes per Hour each.
Electrical re-cabling
The initial estimate included replacement of only 1400 kms of old cable with new cables. However, as degutting progressed and confined spaces were accessed it was realised that an additional 900 kms of cable will need to be replaced. Finally the mammoth task involved replacing 2300 kms of cable, which is a little short of half of the entire coastline of India.
Outfitting
The modification plan of Vikramaditya was not restricted to the gears and sparks alone. The change also necessitated revamp of the living spaces and galleys to cater to the needs of the Indian men in uniform. Of 2500 a total of 1750 compartments were completely re-fabricated. A host of new galley equipment suited for preparation of Indian food like dosas and chapatis was also installed.
Arrestor and Restraining Gears
The conversion of VTOL carrier to STOBAR involved fitment of three 30m wide arrester gears and three restraining gears. Installation of these equipment not only involved modification and strengthening of the flight deck but also changes to internal layout of compartments.
Summary
To sum it up, a total of 234 new hull sections were fabricated using 2500 tonnes of steel which is almost equivalent to the standard displacement of a mid-size frigate. Repair and re-equipping of Vikramaditya to give a new lease of life as a full- fledged carrier was no mean task and was probably as demanding a task as constructing a similar tonnage ship from the drawing board. The task was enabled by the expertise and experience of the Russian designers and yard workers working hand in glove with Indian experts. The extreme cold weather conditions of winter only made the work environment harder. At the end of this refit, spanning a little short of a decade, Vikramaditya has metamorphosed into a fully capable and potent platform.
Rise of the Phoenix …
Vikramaditya sailed for the first time under own power at 1200 hrs on 10 Jun 12, after a gap of about 17 years.
The New Avtar ‘Vikramaditya’
An aircraft carrier carrying potent long range multi-role fighters is a platform inherently deigned for power projection. In as much as ‘Gorshkov’ was transformed to create ‘Vikramaditya’, so also Vikramaditya will transform the face of the Fleet Air Arm of the Indian Navy.
STOBAR Carrier
Displacement: 44,500 T
Length OA: 284 m
Maximum Beam: 60 m
Speed: over 30 kts
04 propellers
powered by 08 Boilers,
Aircraft component:
MiG 29K, Kamov 31, Kamov 28, Seaking, ALH, Chetak